EVM Glossary, F-L
Refer
to this list for definitions of essential earned value management terms submitted
by project managers from around the world. Index: A-E
| F-L | M-Q | R-Z -
F - Fast Tracking The process of
reducing the number of sequential relationships (FS) and replacing them typically
with parallel relationships (SS). FF Link See Finish to Finish link. Filter A
facility allowing subsequent commands to operate only on records that conform
to specified criteria. Finish Date The actual or estimated time associated
with an activitys completion. Finish Float Finish float is the
amount of excess time an activity has at its finish before a successor activity
must start. This is the difference between the start date of the predecessor and
the finish date of the current activity, using the early or late schedule. (Early
and Late dates are not mixed.) This may be referred to as slack time. All floats
are calculated when a project has its schedule computed. Finishing Activity A
finishing activity is the last activity that must be completed before a project
can be considered finished. This activity is not a predecessor to any other activity
-- it has no successors. Many PM software packages allow for multiple finish activities.
Finish-To-Finish Lag The finish-to-finish lag is the minimum amount
of time that must pass between the finish of one activity and the finish of its
successor(s). All lags are calculated when a project has its schedule computed.
Finish-to Finish lags are often used with Start-to-Start lags. Finish-To-Start
Lag The finish-to-start lag is the minimum amount of time that must pass between
the finish of one activity and the start of its successor(s). The default finish-to-start
lag is zero. All lags are calculated when a project has its schedule computed.
In most cases, Finish-to-Start lags are not used with other lag types. Firm
Fixed Price Contract (FFP) A contract where the buyer pays a set amount to
the seller regardless of that sellers cost to complete the project. Fixed
Date A calendar date (associated with a plan) that cannot be moved or changed
during the schedule. Fixed-Duration Scheduling A scheduling method in
which, regardless of the number of resources assigned to the task, the duration
remains the same. Fixed Finish See Imposed Finish. Fixed Price
Contracts A generic category of contracts based on the establishment of firm
legal commitments to complete the required work. A performing contractor is legally
obligated to finish the job, no matter how much it costs to complete. Risks of
all cost growth rest on the performing contractor. Fixed Start See Imposed
Start. Float Float is the amount of time that an activity can slip past
its duration without delaying the rest of the project. The calculation depends
on the float type. See START FLOAT, FINISH FLOAT, POSITIVE FLOAT, and NEGATIVE
FLOAT. All float is calculated when a project has its schedule computed. Forecast
At Completion (FAC) Scheduled cost for a task. Forecast Final Cost See
Estimate at Completion. Forward Pass A procedure within time analysis
to determine the early start and early finish dates of activities. Fragnet See
Subnet. Free Float The maximum amount by which an activity can be delayed
beyond its early dates without delaying any successor activity beyond its early
dates. FS Link See Finish to Start. Functional Manager (FM) The
person responsible for the business and technical management of a functional group. Functional
Matrix An organization type where the project has a team leader in each functional
department and the products are passed from one team to the next. Functional
Organization The hierarchical organization of a staff according to their specialty. Funding
Profile An estimate of funding requirements.
-
G - Gantt (Bar) Chart A Gantt chart is a time-phased graphic display
of activity durations. It is also referred to as a bar chart. Activities are listed
with other tabular information on the left side with time intervals over the bars.
Activity durations are shown in the form of horizontal bars. Gantt, Henry The
inventor of the Gantt Chart. General and Administrative (G&A or GANDA) A
form of indirect expenses incurred for the administration of a company, including
senior executive expenses. Such expenses are spread over the total direct and
burden costs for the company. Goal A one sentence definition of specifically
what will be accomplished, while incorporating an event signifying completion.
- H - Hammocks A hammock groups activities, milestones,
or other hammocks together for reporting. A hammock's milestone number ranges
from 95 to 99. This allows for five levels of summation. For example, two hammocks
at the 95 level can be combined in a 96 level hammock. Any number of hammocks
are allowed within the five levels for a project. Most PM software calculates
the duration of a hammock from the early and late dates of the activities to which
it is linked. Hard Zeros In resource scheduling, there is a distinction
made between resource availabilities specified as zero but which can be exceeded
under certain circumstances, and hard zeros, which can never be exceeded. Hard
zeros may cause an activity to be impossible to schedule, in which case the resource
scheduling process may be aborted.
Hierarchical Coding Structure A coding
system that can be represented as a multi-level tree structure in which every
code except those at the top of the tree has a parent code. Highlight Report A
highlight report reviews progress to date and highlights any actual or potential
problems. The project manager prepares this report at intervals determined by
the project board. Histogram A histogram is a graphic display of resource
usage over a period of time. It allows the detection of overused or underused
resources. The resource usage is displayed in colored vertical bars. The
ideal level for a resource on the screen is indicated by a another color (typically
red). (The printed histogram uses a horizontal line to display the maximum usage
set in the Resource Label window.) If the resource bar extends beyond the red
area for any given day, resources need to be leveled (or spread out) for proper
allocation. The resource histograms should be checked after resources are assigned
to the project activities. Holiday An otherwise valid working day that
has been designated as exempt from work. Hypercritical Activities Activities
on the critical path with negative float. This can be achieved through the imposition
of constraints such as target dates.
- I - Immediate
Activity An activity that can be forced to start on its earliest feasible date
by resource scheduling, even if that means overloading a resource. Impact The
assessment of the adverse effects of an occurring risk. Impact Analysis Assessing
the pros and cons of pursuing a particular course of action. Implementation
Review or Visit An initial visit by members of the customer C/SCSC review team
to a contractors plant to review the contractors plans for implementing
C/SCSC on a new contract. Such visits should take place within 30 days after contract
award. Imposed Finish A finished date imposed on an activity by external
constraints. Imposed Start A start date imposed on an activity by an
external constraint. Indirect Cost Resources expended which are not directly
identified to any specific contract, project, product or service, such as Overhead
and G&A. Individual Work Plan An individual work plan defines the
responsibilities of an individual team member and is the lowest level of a technical
plan. Informal Review A less formal subset of a quality review. Information
Distribution Distributing information to stakeholders in a timely manner. Initiation Committing
the organization to begin a project. In Progress An activity that has
been started, but not yet completed. Integrated Baseline Review (IBR) The
newest form of the Department of Defense C/SCSC verification review process in
which the technical staff lead the effort to verify that the entire project baseline
is in place, together with a realistic budget to accomplish all planned work. Integrated
Cost/Schedule Reporting See Earned Value. Integrated Product Development
Teams (IPDT) The development of new products with use of multi-functional teams,
who work in unison form the conceptual idea until completion of the product. Integrated
product development teams are best contrasted with the traditional form of sequential
functional development. Another term for IPDT is Concurrent Engineering. Integration The
process of bringing people, activities and other things together to perform effectively. International
Project Management Association A federation of European project management
organizations. This does not include PMI or AIPM. Invitation for Bid (IFB) Similar
to a request for proposal, but often with a more specific application area. IT
Executive Committee The departmental top management group that is responsible
for the overall direction of IT projects.
- K
- Key Event Schedule See Master Schedule. Key Performance Indicators Measurable
indicators that will be used to report progress that is chosen to reflect the
critical success factors of the project. KPI See Key Performance Indicators.
- L - Labor Rate Variances Difference between planned
labor rates and actual labor rates. Ladder A sequence of parallel activities
connected at their starts or finishes, or both. Lag Lag is the time delay
between the start or finish of an activity and the start or finish of its successor(s).
See FINISH-TO-FINISH LAG, FINISH-TO-START LAG, and START-TO-START LAG. Late
Dates Calculated in the backward pass of time analysis, late dates are the
latest dates on which an activity can start and finish. Late Event Date Calculated
from backward pass, it is the latest date an event can occur. Late Finish Late
Finish dates are defined as the latest dates by which an activity can finish to
avoid causing delays in the project. Many PM software packages calculate late
dates with a backward pass from the end of the project to the beginning. Late
Start Late Start dates are defined as the latest dates by which an activity
can start to avoid causing delays in the project. Many PM software packages calculate
late dates with a backward pass from the end of the project to the beginning.
Leadership Getting others to follow direction. Level of Effort
(LOE) Work that does not result in a final product (such as liaison, coordination,
follow-up, or other support activities) and which cannot be effectively associated
with a definable end product process result. Level of effort is measured only
in terms of resources actually consumed within a given time period. Leveling See
Resource Leveling. Life-Cycle Costing When evaluating alternatives, Life-Cycle
Costing is the concept of including acquisition, operating and disposal costs. Likelihood Assessment
of the probability that a risk will occur. Line Manager The manager of
any group that makes a product or performs a service. Link See Logical
Relationship. Links See Dependency Links. Logic See Network
Logic. Logic Diagram See Project Network Diagram. Logic Link See
Dependency Links. Logic Loop A circular sequence of dependency links
between activities in a network. Logical Relationship A logical relationship
is based on the dependency between two project activities or between a project
activity and a milestone. Loop In networks, a set of symbols indicating
that one or more activities are mutually dependent.
|